NMHEP is Run of the River project with two generating units of 30 MW each. The second unit of the project is also scheduled to be commissioned within this month. The project will generate 265.5 million units of electricity annually. The Company has constructed 37 km 220 KV Transmission Line for evacuation of power from Naitwar Mori HEP from Bainol to Snail.
Further, after commissioning of this Project, 12% free electricity will be supplied to the State of Uttarakhand as royalty. In addition, each Project Affected Family will be provided with an amount equivalent to cost of 100 Units of electricity per month for ten years.